Commencement of construction works

The first activity in construction works is site clearing. Prior to the commencement of site clearance, survey and setting out coordinate the limit of work according to the construction drawing shall be carried out. Site clearing generally consists of the cutting and /or taking down, removal and disposal of everything above ground level, including objects overhanging the areas to be cleared such as tree branches, vegetation, structures or parts of structures. Clearing of trees, vegetation, undergrowth, bushes and minor structure is carried out by dozers and or hydraulic excavators. Major structure that cannot practically be cleared by hydraulic excavators and/or dozer, these demolition can be carried out using pneumatic tools, explosives and/or other specialized equipment depending on the size and type of structure.
All cut and demolished materials shall be removed and transport using dump trucks to the designated dumping site. Open burning is prohibited by Government Authorities.